40 men, working 8 hours a day can do a piece of work in 15 days. Find the number of days in which second group of 60 men working 4 hrs a day can do twice the work. Assume that 3 men of the first group do as much work in 2 hours as 4 men of the second group do in 3 hrs.

1:
60 days
2:
40 days
3:
80 days
4:
70 days
5:
75 days
Solution:
Chapter Name: Time and Work

This has been asked in Question Paper

IBPS Clerk Mains 2017