Question Paper from: SBI Clerk Prelims 2018

A and B working alone can do a work in 20 days and 15 days respectively. They started the work together but B left after sometime and A finished remaining work in 6 days. Find after how many days from start B left the work ?

1:
5 days
2:
4 days
3:
6 days
4:
3 days
5:
7 days
Solution:
Chapter Name: Time and Work

This has been asked in Question Paper

SBI Clerk Prelims 2018