A, B and C can complete a work in 20, 24 and 30 days respectively. All three of them starts together but after 4 days A leaves the job and B left the job 6 days before the work was completed. C completed the remaining work alone. In how many days was the total work completed?
1:
10
2:
12
3:
16
4:
14
Solution:
Chapter Name: Time and Work